3-phase home battery: CEE 5P connection and installation explained

Introduction

Most Dutch homes are now connected to a three-phase supply (3x25 or 3x35 amps). Nevertheless, many home batteries are still connected to a single phase because plug-in systems are designed for this. If you want to think bigger, with more power or with a home running an electric car, heat pump, and large solar installation, you will quickly end up with a 3-phase home battery. In this article, we explain how such a system works, what the role of the CEE 5P connection is, and what is involved in an installation that complies with the Dutch NEN 1010 standard.

We are explicitly focusing on the multi-phase configuration of the Lunergy Hub 2400 AC. An earlier blog post describes the general installation guide for a single-phase plug-in system: unpacking, placing it, plugging the plug into the socket, connecting the P1 cable to the smart meter, and installing the app. That is sufficient for many households. But if you want to grow into a larger installation with three units and 7.2 kW of power, a separate CEE circuit is involved. How that works exactly, you can read below. Are you unsure whether you need a 3-phase installation at all? Then use the selection guide first.

When do you need a 3-phase home battery?

Dutch households have been supplied with a 3-phase connection as standard since around 2018, mostly 3x25 amps or 3x35 amps. On paper, you therefore have three phases that you can use. Nevertheless, most plug-in home batteries are still connected to only one phase, because the power of those systems remains limited to around 2 to 3 kW and Dutch grid operators do not have major problems with single-phase feed-in or supply.

As soon as you want to go bigger, a 3-phase home battery becomes more attractive. Think of situations in which you want to use more than, for example, 5 kW of storage capacity, where you either have high self-consumption due to a heat pump and a home charging point, or you have a large solar installation of several thousand peak watts that you want to store during the day. In those cases, it helps to distribute the available power over three phases, so that you do not unnecessarily overload one phase.

A second reason is phase balance. If you already have a lot of equipment connected to one phase at home, for example an electric stove on phase 1 and a washing machine on phase 2, then an additional battery on phase 3 can ensure that the load is distributed more evenly across the house. A Hub 2400 AC system with three units can literally do that distribution for you, by placing each unit on its own phase.

Single-phase versus three-phase connection

To feel the difference, it is good to take a look in the meter cabinet. A single-phase connection has one phase (L), a neutral wire (N), and a ground (PE). A 3-phase connection has three phases (L1, L2, L3), a neutral wire, and a ground. The voltage between each phase and the neutral in the Netherlands is 230 volts, and between two phases 400 volts. The main fuse and the residual current protection are connected to those three phases.

You use a single-phase plug-in battery by plugging the regular plug into a wall socket. That is what makes the plug-in home battery attractive: no intervention in the meter cabinet, no electrician needed. The disadvantage is that the maximum usable power remains limited to what is available on that one phase. For most smaller households with a modest solar installation of 2,000 to 3,000 peak watts, that is perfectly sufficient.

A 3-phase installation goes further. Instead of a regular plug, you use a CEE connector (also called an "industrial plug" or "red socket"), and you distribute the charging and discharging current over the three phases. This allows you to use up to 7.2 kW of power with the same type of Hub 2400 AC unit, without unnecessarily heavily loading one phase. For many households with a heat pump or a home charging point, that is the difference between "just enough" and "complete".

What is a CEE 5P connection?

A CEE 5P connector is a red, industrial socket with five pins. Those five pins correspond to three phases (L1, L2, L3), a neutral wire (N), and a protective ground (PE). "5P" therefore literally stands for five poles. In the Netherlands and Belgium, these connectors are often used for connecting campers, power generators, electric charging points, and thus also for larger home battery installations.

The big difference with a regular household socket is that the CEE connector is built to continuously carry higher currents, and that it locks mechanically. This prevents the plug from accidentally coming loose, and the socket is better resistant to moisture and dust. For a 3-phase home battery, that is exactly what you want: a safe, fixed connection that can pass through a good deal of kW of energy day in, day out.

Important: a CEE 5P connection in the meter cabinet is not a do-it-yourself job. Installing a separate circuit, mounting a residual current circuit breaker, and connecting the three phases belong to a certified installer who knows the NEN 1010 standard. The plug-in concept of the Hub 2400 AC means that you as a user do not have to screw the units into the meter cabinet yourself, but you should have the CEE circuit itself installed correctly.

Multiple Hub units, each on its own phase

The way Lunergy approaches a 3-phase system is relatively simple: instead of connecting one inverter to the three phases, you place multiple Hub 2400 AC units, and you assign each unit one phase. One Hub unit goes on L1, the second on L2, and the third on L3. Each unit therefore remains an independent, plug-in device, but together they virtually form a 3-phase installation.

That approach has a number of practical advantages. Firstly, the installation remains modular: you start with one unit on one phase and can later easily add two extra units if you need them. Secondly, you do not have to invest in an expensive inverter specially designed for 3-phase. Thirdly, maintenance remains simple, because each unit can be read out or replaced independently of the others.

The control under those units does a joint job. Via the P1 port of the smart meter, the system sees what is coming in or being fed back on each phase, and via the app, the distribution is monitored. The AI-controlled regulation looks not only at the total surplus of your solar panels, but also at how the load is distributed over the phases. Read more about that P1 control in the installation guide.

The top configuration: 31.32 kWh and 7.2 kW

The most extensive configuration you can build with the Hub 2400 AC consists of three Hub units plus six BP5200 expansion modules. Together providing 31.32 kWh of capacity and 7.2 kW of power. That is an installation comparable to what you see with traditional, custom-installed home batteries, but built from modular, plug-in components.

That top configuration is suitable for larger families with a substantial solar installation and high self-consumption, for example because a heat pump, an electric car, and an extensive home network are running. In practice, 31.32 kWh means that you can amply buffer a sunny day to provide your own electricity in the evening and at night, without constantly feeding it directly back to the grid. Note: the system remains a plug-in solution with a maximum backup power per unit of 2.4 kW, so it is not a full off-grid solution for a whole house.

Below that, there are two more interesting steps. With two Hub units and four modules, you end up with 20.88 kWh and 4.8 kW. With one Hub and three modules, you keep it at 15.66 kWh and 2.4 kW. The prices range from €1,499 for the basic of 5.22 kWh and 2.4 kW, to €7,397 for the top of 31.32 kWh and 7.2 kW. In our comparison of 5 kWh and 10 kWh, you can read more about the right size.

NEN 1010 and the role of the certified installer

The NEN 1010 is the Dutch standard that regulates electrical installations in homes. It states, among other things, what requirements a circuit cabinet must meet, how the residual current protection is arranged, and how 3-phase circuits must be correctly connected. For a 3-phase CEE installation, it is important that the circuit is separately protected, that a suitable residual current circuit breaker is installed, and that the wire thicknesses match the expected current.

If you choose a 3-phase version, then it is therefore important to have the meter cabinet checked by a certified installer. They check if your existing circuit cabinet is suitable to add a CEE 5P circuit, or if an expansion or replacement of the cabinet is needed. In many more modern homes, there is enough space, in older homes with a small cabinet, something may need to be added.

For the rest of the installation, the advantage of the plug-in approach applies: you do not have to open the entire meter cabinet and mount the inverter in the cabinet. The Hub units remain freestanding on the floor, and only the CEE plug runs back to the circuit cabinet. That saves installation time and you can easily move the units later. Our manual describes the steps involved.

Preparation and what you do and do not do yourself

What can you do yourself before the installer comes by? Think of determining the location for the Hub units: a cool, dry indoor space with enough floor space and a socket nearby. Make sure that the CEE cable path runs easily, without having to go over thresholds or under door posts. Also take photos of your current circuit cabinet, so the installer can assess beforehand what is needed.

What you better do not do yourself is the installation of the CEE circuit in the meter cabinet, the mounting of the residual current circuit breaker, and the connection of the phases. That is professional work and falls under the NEN 1010 standard. The installer also ensures that the meter cabinet is correctly deregistered with the grid operator, if that is necessary. In Belgium, the Synergrid recognition applies as a reference point; Lunergy systems are certified on that.

After placement, you connect the P1 cable yourself to your smart meter, install the app, and assign the correct phase per Hub unit. That last step is important: an incorrect phase assignment causes the balance over the phases to be incorrect. In the manual, you can read how you check that. Do you want to know more about how the battery deals with a power outage? Then read our article about backup during a power outage.

Conclusion

A 3-phase home battery is not an unnecessary luxury if you want to go further than a simple plug-in solution. With the CEE 5P connector and three Hub units, each on its own phase, you build a modular system up to 31.32 kWh of capacity and 7.2 kW of power. You leave the installation of the CEE circuit to a certified installer according to NEN 1010; the rest of the setup remains plug-in and simple.

Are you unsure whether you really need three units, or if you can also make do with one or two units? Then use the selection guide, view the product page, or contact us via contact. We are happy to think along with you about the right dimension for your situation.

Frequently asked questions about a 3-phase home battery

Do I need a 3-phase home battery?

That depends on your consumption and your solar installation. For most households, a single-phase plug-in Hub 2400 AC of 2.4 kW is sufficient. A 3-phase system is interesting if you want to grow into more power (up to 4.8 or 7.2 kW), have a heat pump or home charging point, or if you would like to distribute the load evenly over the three phases. Use the selection guide to get an indication.

What is a CEE 5P connection?

A CEE 5P connector is a red industrial plug socket with five poles: three phases (L1, L2, L3), a neutral wire (N), and a protective ground (PE). The connector is lockable and suitable for continuous higher currents. For a 3-phase home battery, that is the way to connect the system safely and fixedly to the meter cabinet.

Can I install the CEE connection myself?

No, the installation of a CEE 5P circuit in the meter cabinet, including residual current circuit breaker and phases, belongs to a certified installer who works according to the NEN 1010 standard. The plug-in concept of the Hub 2400 AC means that you do not have to screw the units into the meter cabinet yourself, but you have the fixed CEE connection installed correctly.

How much power and capacity can I build up at most?

With three Hub 2400 AC units and six BP5200 modules, you build up to 31.32 kWh of capacity and 7.2 kW of power. In between, there are steps of 5.22 kWh plus 2.4 kW, 10.44 kWh plus 2.4 kW, 15.66 kWh plus 2.4 kW, and 20.88 kWh plus 4.8 kW. Note: kW (power) and kWh (capacity) are different quantities.

Does a 3-phase system also work as backup during a power outage?

The Hub 2400 AC has a UPS function with a switching time of less than 10 milliseconds, with which you can continue to power connected devices. Per unit, however, the backup power is at most 2.4 kW; so it is not a full off-grid solution for a whole house. Read more about that in our article about backup during a power outage.

Is a 3-phase system suitable in Belgium?

Yes, the Hub 2400 AC is Synergrid-certified, regarding the Belgian connection conditions. For placement in Belgium, similar rules apply as in the Netherlands: you have the CEE circuit installed by a certified installer. For specific situations, contact us via contact.

View the Lunergy Hub 2400 AC or use the selection guide to see if a 3-phase configuration fits your situation.